LO4 Demo Script for SAP S/4HANA 2025 SP00 Fully-Activated Appliance: Plan to Produce using Advanced Planning for Capacity Utilization
© 2025 SAP SE or an SAP affiliate company. All rights reserved. See Legal Notice on www.sap.com/legal-notice for use terms, disclaimers, disclosures, or restrictions related to this material.
PUBLIC
SAP S/4HANA 2025 SP00 Fully-Activated Appliance
November 2025
Demo Guide:
Plan to Produce Using Advanced Planning for Capacity
Utilization
PUBLIC
SAP S/4HANA 2025 SP00 Fully-Activated Appliance
November 2025
Demo Guide:
Plan to Produce Using Advanced Planning for Capacity
Utilization
Table of Contents
1 Where Can This Script Be Used? 3
1.1 Passwords for the pre-configured demo users 3
2 Demo Story: Plan to Produce Using Advanced Planning for Capacity Utilization 4
2.1 Preliminary Steps 4
2.1.1 Post Initial Stock 4
2.1.2 Check Stock Level 6
2.2 Create Planned Independent Requirements 7
2.3 Run Material Requirement Planning 8
2.4 Monitor Capacity Utilization 10
2.5 Create Production Order for Semifinished Product 25
2.6 Release Production Order for Semifinished Product 26
2.7 Confirm Production Order for Semifinished Product 28
2.8 Post Goods Receipt for Semifinished Production Order 31
2.9 Manage Inspection Lot 32
2.10 Create Production Order for the Finished Good 33
2.11 Release Finished Goods Order 35
2.12 Confirm Production for Finished Product 36
2.13 Post Goods Receipt for Production Order 39
Document History
Revision Date Change
1.0 <2020-06-02> Release for customer for S/4HANA 1909 FPS02
2.0 <2021-04-15> Release for customer for S/4HANA 2020 FPS01
2.1 <2021-07-08> Release for customer for S/4HANA 2020 FPS02
2.2 <2022-03-31> Release for customer for S/4HANA 2021 FPS01
2.3 <2022-06-28> Release for customer for S/4HANA 2021 FPS02
2.4 <2022-12-06> Release for customer for S/4HANA 2022 FPS00
2.5 <2023-06-06> Release for customer for S/4HANA 2023 FPS02
2.6 <2023-10-24> Release for customer for S/4HANA 2023 SP00
2.7 <2024-03-24> Release for customer for S/4HANA 2023 FPS01
2.8 <2024-11-01> Release for customer for S/4HANA 2023 FPS02
2.9 <2025-04-01> Release for customer for S/4HANA 2023 FPS03
3.0 <2025-11-01> Release for customer for S/4HANA 2025 SP00
1 Where Can This Script Be Used? 3
1.1 Passwords for the pre-configured demo users 3
2 Demo Story: Plan to Produce Using Advanced Planning for Capacity Utilization 4
2.1 Preliminary Steps 4
2.1.1 Post Initial Stock 4
2.1.2 Check Stock Level 6
2.2 Create Planned Independent Requirements 7
2.3 Run Material Requirement Planning 8
2.4 Monitor Capacity Utilization 10
2.5 Create Production Order for Semifinished Product 25
2.6 Release Production Order for Semifinished Product 26
2.7 Confirm Production Order for Semifinished Product 28
2.8 Post Goods Receipt for Semifinished Production Order 31
2.9 Manage Inspection Lot 32
2.10 Create Production Order for the Finished Good 33
2.11 Release Finished Goods Order 35
2.12 Confirm Production for Finished Product 36
2.13 Post Goods Receipt for Production Order 39
Document History
Revision Date Change
1.0 <2020-06-02> Release for customer for S/4HANA 1909 FPS02
2.0 <2021-04-15> Release for customer for S/4HANA 2020 FPS01
2.1 <2021-07-08> Release for customer for S/4HANA 2020 FPS02
2.2 <2022-03-31> Release for customer for S/4HANA 2021 FPS01
2.3 <2022-06-28> Release for customer for S/4HANA 2021 FPS02
2.4 <2022-12-06> Release for customer for S/4HANA 2022 FPS00
2.5 <2023-06-06> Release for customer for S/4HANA 2023 FPS02
2.6 <2023-10-24> Release for customer for S/4HANA 2023 SP00
2.7 <2024-03-24> Release for customer for S/4HANA 2023 FPS01
2.8 <2024-11-01> Release for customer for S/4HANA 2023 FPS02
2.9 <2025-04-01> Release for customer for S/4HANA 2023 FPS03
3.0 <2025-11-01> Release for customer for S/4HANA 2025 SP00
© 2025 SAP SE or an SAP affiliate company. All rights reserved. See Legal Notice on www.sap.com/legal-notice for use terms, disclaimers, disclosures, or restrictions related to this material.
3
1 Where Can This Script Be Used?
This demo script has been written for usage with the SAP S/4HANA 2025 SP00 Fully-Activated Appliance (in short “appliance” in
this script), hence you will need such an appliance to make use of this guide.
The appliance can be brought up in two ways, and the demo scenario in this script is largely the same for both:
1. Via SAP Cloud Appliance Library (hosted on cloud providers)
You need a cloud provider account at AWS, MS Azure, or GCP. With this, you can deploy the appliance within 1-2 hours from
https://cal.sap.com > Solutions > SAP S/4HANA <Your Release> Fully-Activated Appliance.
2. Via installing it on your own on-premise hardware.
You need to provide your own hardware, and order & install the appliance as explained in SAP Note 2041140.
If you are new to the SAP S/4HANA Fully-Activated Appliance, introductory information can be found here:
https://blogs.sap.com/2018/12/12/sap-s4hana-fully-activated-appliance-create-your-sap-s4hana-1909-system-in-a-fraction-of-
the-usual-setup-time/
Important:
Before you start your demo, please read SAP S/4HANA Fully-Activated Appliance: Demo Scripts for information about necessary
preparations, especially any post-deployment steps to ensure the full functionality of your appliance. These steps are covered in
sections;
B) General Remarks
C) Post-deployment Steps
D) Log-on to the system
Besides this, you will also find links to all demo scripts on this page.
1.1 Passwords for the pre-configured demo users
Please contact your company’s system administrator for your company-specific demo user passwords. Demo users provided in
the appliance which are used for the Demo Scripts were delivered with the password “Welcome1”, however SAP recommends
changing these.
If you experience user/logon issues, please contact your team’s SAP S/4HANA Appliance system administrator.
3
1 Where Can This Script Be Used?
This demo script has been written for usage with the SAP S/4HANA 2025 SP00 Fully-Activated Appliance (in short “appliance” in
this script), hence you will need such an appliance to make use of this guide.
The appliance can be brought up in two ways, and the demo scenario in this script is largely the same for both:
1. Via SAP Cloud Appliance Library (hosted on cloud providers)
You need a cloud provider account at AWS, MS Azure, or GCP. With this, you can deploy the appliance within 1-2 hours from
https://cal.sap.com > Solutions > SAP S/4HANA <Your Release> Fully-Activated Appliance.
2. Via installing it on your own on-premise hardware.
You need to provide your own hardware, and order & install the appliance as explained in SAP Note 2041140.
If you are new to the SAP S/4HANA Fully-Activated Appliance, introductory information can be found here:
https://blogs.sap.com/2018/12/12/sap-s4hana-fully-activated-appliance-create-your-sap-s4hana-1909-system-in-a-fraction-of-
the-usual-setup-time/
Important:
Before you start your demo, please read SAP S/4HANA Fully-Activated Appliance: Demo Scripts for information about necessary
preparations, especially any post-deployment steps to ensure the full functionality of your appliance. These steps are covered in
sections;
B) General Remarks
C) Post-deployment Steps
D) Log-on to the system
Besides this, you will also find links to all demo scripts on this page.
1.1 Passwords for the pre-configured demo users
Please contact your company’s system administrator for your company-specific demo user passwords. Demo users provided in
the appliance which are used for the Demo Scripts were delivered with the password “Welcome1”, however SAP recommends
changing these.
If you experience user/logon issues, please contact your team’s SAP S/4HANA Appliance system administrator.
© 2025 SAP SE or an SAP affiliate company. All rights reserved. See Legal Notice on www.sap.com/legal-notice for use terms, disclaimers, disclosures, or restrictions related to this material.
4
2 Demo Story: Plan to Produce Using Advanced
Planning for Capacity Utilization
This demo story describes the end-to-end scenario for planning and producing a finished product using both raw materials as well
as semi-finished goods. The focus is set on the advanced capabilities of the “Monitor Capacity Utilization” app which helps a
planner to monitor, plan and correct any capacity overload issues.
Note:
Depending on the release / feature package stack (FPS) that you are using, the screens might look a bit different due to different
Fiori themes used. You can toggle the Fiori themes under User profile → Settings.
2.1 Preliminary Steps
2.1.1 Post Initial Stock
In a real business case, the raw materials or the semi-finished products can be purchased from external vendors; in that case, that
process is covered by the standard purchasing or subcontracting processes. In this demo story, for all raw materials (RM20 and
RM124), initial stock is posted using movement type 501.
What to Do What You Will See
Open the Fiori
Launchpad.
User: S4H_PP_DEM
Password: Welcome1
or see section 1.1
Choose the:
Post Goods Receipt
Without Reference app.
In the Goods Receipt
Without Reference
view, click on the item
line.
4
2 Demo Story: Plan to Produce Using Advanced
Planning for Capacity Utilization
This demo story describes the end-to-end scenario for planning and producing a finished product using both raw materials as well
as semi-finished goods. The focus is set on the advanced capabilities of the “Monitor Capacity Utilization” app which helps a
planner to monitor, plan and correct any capacity overload issues.
Note:
Depending on the release / feature package stack (FPS) that you are using, the screens might look a bit different due to different
Fiori themes used. You can toggle the Fiori themes under User profile → Settings.
2.1 Preliminary Steps
2.1.1 Post Initial Stock
In a real business case, the raw materials or the semi-finished products can be purchased from external vendors; in that case, that
process is covered by the standard purchasing or subcontracting processes. In this demo story, for all raw materials (RM20 and
RM124), initial stock is posted using movement type 501.
What to Do What You Will See
Open the Fiori
Launchpad.
User: S4H_PP_DEM
Password: Welcome1
or see section 1.1
Choose the:
Post Goods Receipt
Without Reference app.
In the Goods Receipt
Without Reference
view, click on the item
line.
© 2025 SAP SE or an SAP affiliate company. All rights reserved. See Legal Notice on www.sap.com/legal-notice for use terms, disclaimers, disclosures, or restrictions related to this material.
5
What to Do What You Will See
The Goods Receipt
Item view displays.
In the Material section,
make the following
entries:
Material: RAW20,PD
Quantity/Unit:3000
Alternative Unit of
Measure: PC
In the Plant Options /
Stock Type section,
make the following
entries and choose
Apply and New:
Plant: 1710
Storage Location: 171B
Stock Type:
Unrestricted-Use
Choose the Apply and
New button.
Repeat the steps
above for material
RM124.
In the Materials
section, make the
following entries:
Material: RM124
Quantity/Unit:3000
Alternative Unit of
Measure: PC
In the Plant Options /
Stock Type section,
make the following
entries and choose
Apply:
Plant: 1710
Storage Location: 171B
Stock Type:
Unrestricted-Use
Choose Apply.
Choose Post.
A successful message
displays with the ID of
material document
posted.
4900008954/2025
5
What to Do What You Will See
The Goods Receipt
Item view displays.
In the Material section,
make the following
entries:
Material: RAW20,PD
Quantity/Unit:3000
Alternative Unit of
Measure: PC
In the Plant Options /
Stock Type section,
make the following
entries and choose
Apply and New:
Plant: 1710
Storage Location: 171B
Stock Type:
Unrestricted-Use
Choose the Apply and
New button.
Repeat the steps
above for material
RM124.
In the Materials
section, make the
following entries:
Material: RM124
Quantity/Unit:3000
Alternative Unit of
Measure: PC
In the Plant Options /
Stock Type section,
make the following
entries and choose
Apply:
Plant: 1710
Storage Location: 171B
Stock Type:
Unrestricted-Use
Choose Apply.
Choose Post.
A successful message
displays with the ID of
material document
posted.
4900008954/2025