SAMPLE QUESTIONS: C_TSCM42_60

SAP Certified Application Associate – Planning & Manufacturing with SAP ERP 6.0 – print view

Disclaimer: These sample questions are for self-evaluation purposes only and do not appear on the actual certification exams. Answering the sample questions correctly is no guarantee that you will pass the certification exam. The certification exam covers a much broader spectrum of topics, so do make sure you have familiarized yourself with all topics listed in the exam competency areas before taking the certification exam.

Questions

1. What options does the SAP ECC system offer for retrieving the available capacity for work centers?

There are three correct answers to this question. Select which of the following answers are correct.

a)

O

Attendance list

b)

O

Standard available capacity

c)

O

Shift plan

d)

O

Interval of available capacity

e)

O

Shift sequence

2. You enter a new BOM in SAP ECC but forget to enter a plant reference. Which of the following statements is true regarding what happens when you try to save it?

Please select the correct answer.

a)

O

When saving the BOM, a group BOM is created which can, under certain conditions, be assigned to a plant later.

b)

O

When saving the BOM, a dialog box appears prompting the user to enter a plant.

c)

O

When saving the BOM, an error message appears stating that it is not possible to save a BOM without a plant reference.

d)

O

When saving the BOM, a warning message appears. In the corresponding dialog box, it is possible to create a plant-specific engineering BOM.

3. In the SAP ECC system, you interpret the result of a routing schedule.
When scheduling a routing in the SAP ECC system, which of the following time elements are transition times?

There are two correct answers to this question. Select which of the following answers are correct.

a)

O

Safety time

b)

O

Floats before and after production

c)

O

Processing time

d)

O

Transportation time

4. During the implementation of SAP ECC material requirements planning the project team defines MRP controller numbers in Customizing under the entry "Define MRP Controller" that can be assigned to the planners responsible for the material.
Which statements about these MRP controller numbers are true?

There are two correct answers to this question. Select which of the following answers are correct.

a)

O

The MRP controller number is a central selection criterium for evaluating material requirements planning.

b)

O

A planner responsible for a material can have multiple MRP controller numbers.

c)

O

In multilevel single-item planning, materials are selected using the MRP controller number.

d)

O

The MRP controller number is assigned using the production version.

5. The customer you are advising uses a plant data collection system from the XYZ company and would like to dsitribute production orders to the terminals of this system as well as entering feedback using these terminals. Which integration possibilities would you recommend so that as little work as possible is required for the customer to implement this?

Please select the correct answer.

a)

O

SAP Manufacturing Integration and Intelligence(SAP MII)

b)

O

The plant data collection interface (PP-PDC)

c)

O

Execution steps (XSteps)

d)

O

The process control system inteface PI-PCS

6. Which of the following possibilities for the implementation of plan-in production orders are available?

There are three correct answers to this question. Select which of the following answers are correct.

a)

O

Mass processing

b)

O

Automatically in the planning run (MRP)

c)

O

Background processing in a program

d)

O

Customizing for the planned order

e)

O

Order progress report

7. You have a project in an integrated network consisting of SAP ECC and SAP SCM-APO and are mapping the program planning for an important end product in SAP SCM-APO.
In which system (SAP ECC or SAP SCM) can the corresponding primary requirements (sales orders, planned independent requirements) be administered?

There are two correct answers to this question. Select which of the following answers are correct.

a)

O

Planned independent requirements can be administered in SAP ECC or SAP SCM-APO.

b)

O

Sales orders can be administered in SAP ECC or SAP SCM-APO.

c)

O

Sales orders can only be administered in SAP ECC.

d)

O

Sales orders can only be administered in SAP SCM-APO.

e)

O

Planned independent orders can only be administered in SAP ECC.

8. Which statements are true for the reorganization of planned independent requirements in SAP ECC?

There are two correct answers to this question. Select which of the following answers are correct.

a)

O

The reorganization only affects planned independent requirements that lie on a time axis to the past from a specified key date.

b)

O

The reorganization can be parameterized using a plant-specific reorganization interval.

c)

O

The reorganization only deletes planned independent requirements that have no fixed planned orders to them.

d)

O

The reorganization is a form of demand adjustment that is undertaken in the planning group and only sets the status of non-settled planned independent requirements for the planning to inactive but does not delete them.

9. Which BOM selection possibilities are available for opening a production order?

There are tow correct answers to this question. Select which of the following answers are correct.

a)

O

Manual selection

b)

O

Automatic selection controlled with Customizing settings

c)

O

Selection by BOM number in the material master of the material to be produced

d)

O

Selection using the production scheduling profile

e)

O

Selection using a production version

Solutions

1 a) Incorrect

2 a) Correct

3 a) Incorrect

4 a) Correct

5 a) Incorrect

1 b) Correct

2 b) Incorrect

3 b) Correct

4 b) Correct

5 b) Correct

1 c) Incorrect

2 c) Incorrect

3 c) Incorrect

4 c) Incorrect

5 c) Incorrect

1 d) Correct

2 d) Incorrect

3 d) Correct

4 d) Incorrect

5 d) Incorrect

1 e) Correct

 

 

 

 

6 a) Correct

7 a) Correct

8 a) Correct

9 a) Incorrect

 

6 b) Incorrect

7 b) Incorrect

8 b) Correct

9 b) Correct

 

6 c) Correct

7 c) Correct

8 c) Incorrect

9 c) Incorrect

 

6 d) Incorrect

7 d) Incorrect

8 d) Incorrect

9 d) Incorrect

 

6 e) Correct

7 e) Incorrect

 

9 e) Correct

 

To register for training courses or certification exams, contact the customer interaction center at +1-888-777-1727, option 1.

Save
Share OptionsShare
Site Map  Investors  Careers  Inside Access  Communities  Education and Training  ASUG  Contact SAP
Copyright/Trademark  Privacy  Impressum  Using SAP.com  Text-Only View  Print View

Questions or comments about the Web site?
Contact the webmaster@sap.com.